Installations for an Abattoir in the Central West Region as part of their Upgrades

Installations for an Abattoir in the Central West Region as part of their Upgrades

 

  • Supply and Install of 1 MVA Padsub
  • Supply and Install of 1 x 63 kVA Padsub

  • Supply and Install of 1 x 500 kVA backup generator with Auto start and custom transfer switch

  • Supply and Install if 1 x 1 MVA backup generator with Auto start and custom transfer switch with radio controls to the power factor correction units
  • Supply and install of Custom built 1600 A switchboard to replace the existing dated switchboard
  • Supply and install of Custom built 630 A switchboard to replace the existing dated switchboard
  • Supply and install of 125 A custom built switchboard
  • Supply and install of 400 kVAR Power Factor Correction Unit(PFC)
  • Maintaining the overhead powerline network
  • Replaced the ware house lights with LEDS
  • All electrical install to support the biodigester and biogas generators which supplies part of the abattoir from 400 m away.